Ethical Innovative Dependable

Risk Managers, Technical Consultants & Insurance Brokers

Experts and Engineers as Partners to Support, Secure and Grow your Business Financially, Economically, Globally.

Articles Contact Us Get a Quote
HomePage
EMail
Facebook
Twitter
LinkedIn

Corporate Insurance

Contractor's All Risk Policy


Download forms for this policy

Highlights

This policy is specially designed to give financial protection to the Civil Engineering Contractors in the event of an accident to the civil engineering works under construction.

In case the policy period exceeds 12 months, the premium can be paid in quarterly installments with the first installment being more by 5% and the last installment being paid 6 months before expiry of the policy.

Who can take the policy?

The policy can be taken by the principal, contractor or sub contractor, jointly or separately.

Scope

The policy comprises of 2 Sections :

Section I

Material Damage-covering physical loss, damage or destruction of the property insured by any cause, other than those specifically excluded in the policy.

Section II

Third Party Liability-covering the legal liability falling on the insured contractor as a result of bodily injury or property damage belonging to a third party.

Exclusions

The main exclusions under Section I for which no claim is payable, are loss or damage due to:

Add on covers

The policy can be extended to cover the following items :

How to select the sum insured?

The sum insured selected under section I should represent total contract value including the estimated cost of labour charges and cost of materials but excluding profit. The cost of materials supplied by the principal is to be declared separately.

In case of long term contracts, there is bound to be escalation in prices. The basic policy will pay only as per the original cost and prices. However escalation clause can be opted for, under which escalation upto 50%, can be selected to take care of such increase in prices.

The sum insured under section II should represent the per accident limit (the maximum legal liability that may fall on the insured as a result of an accident in the insured's site). The limit per policy period should be fixed taking into account the maximum number of such accidents which can reasonably be expected to occur.

Period of Insurance

Unlike other policies where the period of insurance is one year, in this policy the period of insurance should be equivalent to the period of contract,commencing from the date of unloading of the first batch of material at the site of construction and expiring on the date of handing over of the contract work to the principal.

Although it is possible to extend the policy period in case of delay in completion of contract, it is always advisable to choose a slightly longer period of insurance initially, to avoid paying the higher extension premium.

How to claim?

In the event of any loss or damage giving rise to a claim under the policy, the following steps should be taken :


Note : Policy details offered are indicative, not exhaustive. Please contact your nearest Arunaya office for further details.